Blu Line/Rosegate

Here are new plans that were submitted by the developer last night:







These are copies of the site plan:




Some of the feedback given by the Planning Commission:
  • Per the design guidelines, the landscaping in the area is supposed to be park-like and to be enjoyed by the community. The majority of the park-like areas for this facility are enclosed and will only be seen by the residents who live in the facility. Here is a copy of the open space layout:
  • Guidelines state the facade should be broken up, but the south portion is one long facade.
  • Over 50% of the facade is stucco or siding, in the past the discussions included more brick and colonial style materials. This doesn't feel colonial and doesn't match the rest of the commercial area.
  • The architecture is vanilla and past rendering looked better.
The developer did provide the following comparison of services; however, he did not indicate which of these services are offered onsite as part of the facility and which services will be outsourced to other companies, such as home health agencies.


The current height of the building is 37' to the top and 35' to the midline. The total square footage is 118,000.

The Planning Commission tabled this item as there were several concerns with the drawings provided. They agreed to hold a special meeting within the next week to review updated plans.


Lakeview Trails - The final plans for Lakeview Trails (a residential subdivision on the east side of Canyon Road) were approved and will go to the City Council.